CONSTRUCTION UPDATES

Structure and Brickwork Complete

6th & 7th Floor Level

Structure and Brickwork Completed

Fifth Floor Level

Fifth Slab Shuttering Work is in progress

Fourth Floor Level

Fourth Slab Casting Completed

Third Floor Level

Brickwork is in progress.

Second Floor Level

Second Floor 25% work completed, reinforcement and electrical work of remaining is in progress.

First Floor Level

Shuttering of floor slab and column work is in progress

Stilt Level

Stilt Floor included Parking, Grand Lobby and Function Area, work completed in part, work in progress in other part.

Basement Casting

Upto Dec 2019

Casting work done using high quality material from TATA Steel and Ultratech Concrete.

Foundation Preparation

Upto Nov 2019

Foundation Work done in record time earlier than expected schedule.

Site Preparation Excavation

Start to Oct 2019

Site Preparation and Excavation Work Started simultaneously while obtaining RERA Registration to deliver on time.